Appendix 7 · Practical Example

When Investment Runs Ahead of the Evidence

1. Executive Summary

An approved investment, an appointed project team and eight months of activity had not produced an executable warehouse relocation plan. Gary Newbury challenged unreliable assumptions, rebuilt the operational evidence, developed an accepted blueprint and mobilized the client team around a critical-path implementation programme.

2. Context and Need for Intervention

An automotive aftermarket logistics provider generated $160 million in revenue and held $40 million in inventory. Following the loss of a major manufacturer contract, it needed to leave a large, landlocked warehouse for a smaller purpose-built facility.

The operational fit-out budget was $5 million, with targeted annual operating savings of $1.4 million. Construction decisions were approaching and the existing facility had a fixed exit deadline.

Design activity continued without dependable capacity assumptions, an agreed solution or an integrated route to opening.

3. Establishing Reality

Gary identified three underlying weaknesses:

Unreliable investment evidence: product dimensions, capacity requirements, labour assumptions and operating economics did not adequately support facility decisions.

Activity without accountability: workstreams lacked integrated milestones, ownership and decision discipline.

Existing weaknesses entering the future model: excess inventory and inefficient processes risked becoming permanent features of the new facility.

One calculation crystallized the problem. The internal design suggested one vertical carousel for a substantial part of the inventory. Gary’s preliminary analysis suggested nearer 27. The discrepancy exposed the danger of treating diverse physical products as an aggregate volume calculation.

Gary directed a six-week measurement exercise using specialist equipment. The team measured almost the entire 65,000-product range, establishing a defensible basis for storage design.

The inventory review also exposed $8 million in excess and long-held stock.

Capital investment can make an unresolved weakness harder to remove when the new facility is designed around it.

4. Leadership and Decision Rights

The interim CEO sponsored Gary’s work with the project team and finance, operations and technology leaders.

Gary challenged assumptions that lacked evidence and established the revised direction with the sponsor and senior colleagues. His mandate centred on developing the solution and preparing the organization to implement it.

Some workstream owners were ready to proceed; others required direct engagement over the responsibilities and pace needed.

5. Intervention and Operating Changes

Gary designed a combination of pallet racking, cantilever storage, shelving and selected vertical carousels appropriate to actual product characteristics and handling requirements. The design used the building’s height and allowed for projected product-range growth.

He connected layout and material flow to receiving, replenishment, picking, dispatch, staffing and the targeted savings. Retaining the existing warehouse management platform avoided adding an unfamiliar system to an already demanding relocation.

The proposed fit-out aligned with the $5 million budget, including suitable equipment reuse. Specialist engineering support strengthened the design and planning.

Gary then developed an integrated programme with dependencies, milestones, a critical path and named workstream owners. Individual meetings established commitments. A formal kickoff transferred the programme into client ownership, followed by several days of support to reinforce action and resolve outstanding documentation.

6. Results and Transfer

The assignment delivered an accepted operating blueprint and a mobilized implementation programme.

Physical product measurements replaced inadequate assumptions. The principal layout, storage methods, process direction, capacity allowance and systems approach were established. The $8 million inventory opportunity offered a route to release working capital rather than spend more capital storing unnecessary stock.

The design supported the $5 million fit-out budget and targeted $1.4 million annual operating savings. Client workstream owners assumed responsibility for procurement, configuration, relocation and operational launch.

Client testimonial

“Gary didn’t just design a warehouse, he gave us the commercial case, the delivery plan, and the urgency we were missing. He got it moving when no one else could.”

Interim Chief Executive, automotive aftermarket logistics provider

7. What This Practical Example Demonstrates

Gary turned accumulated project activity into a decision supported by operating evidence and an accountable delivery plan. The work corrected the assumptions before they became costly physical commitments.

An approved budget is not an executable decision. Reliable evidence and clear ownership make the difference.

Intervention Pathway: RADAR with blueprint development and implementation mobilization.Delivery Model: Gary-led investigation and design; assisted mobilization followed by client-led implementation.

Gary Newbury
Senior Interim Executive — Reliable Performance Recovery & Operating Model Transformation