1. Executive Summary

A $25 million international accessories supplier wanted to triple sales within five years. Its distribution network already struggled with inventory, cost and lengthy replenishment. Gary Newbury developed a global fulfilment blueprint and worked with the CFO to establish $8 million in projected annual savings. He subsequently returned to help the management team begin implementation.

2. Context and Need for Intervention

Components moved from factories into an assembly and storage operation, then travelled predominantly by ocean freight to regional warehouses.

The arrangement worked when requirements were predictable. When major customers changed orders at short notice, stock was frequently in the wrong location. Routine replenishment could take six to eight weeks, with emergency air freight providing an expensive alternative.

The growth ambition made the existing weaknesses more consequential. Expanding the same arrangements risked multiplying inventory, handling and exceptional transport rather than building dependable global service.

3. Establishing Reality

Gary investigated physical flows, inventory, processes, systems and economics across the international network, working alongside a technology specialist.

Three weaknesses became apparent:

Inventory positioned around warehouses: multiple holdings increased working capital, handling and obsolescence without guaranteeing availability.

Transport decisions detached from total cost: inexpensive ocean movements created long replenishment cycles, while emergency air freight compensated for shortages.

Fragmented fulfilment design: configuration, packaging, allocation and information systems did not support rapid global response.

The investigation identified $2.5 million in excess and obsolete inventory. Gary concluded that more warehouses and larger buffers would preserve the weakness.

A low transport rate can be an expensive choice when the wider operating model creates excess stock, repeated handling and emergency shipments.

4. Destination and Design Decisions

Gary developed the transformation blueprint: hold components nearer manufacture, delay final configuration and dispatch consolidated customer orders through a global fulfilment hub.

He worked directly with the CFO to identify the costs that would change as regional warehouses, duplicated handling and emergency freight were replaced. Together, they established the projected $8 million annual savings.

Gary led the design. He then returned to assist the management team in translating the blueprint into implementation delivery.

5. Intervention and Operating Changes

The blueprint connected five changes:

Upstream inventory: manufacturers would retain more components, replenishing the hub through smaller, more frequent movements.

Rapid fulfilment: the hub would configure, consolidate and dispatch customer orders, supported by strategic buffers for the 25 highest-volume products.

Planned air transport: consolidated shipments and standardized cartons would replace lengthy routine replenishment and emergency movements.

Network simplification: unnecessary regional warehouses would close progressively.

Systems support: receiving, allocation, assembly and dispatch workflows would be supported by specified software functionality.

The design targeted 48–72-hour global fulfilment, with next-day capability for priority products in core markets.

During assisted implementation, warehouse termination notices were issued, stock clearance progressed, supplier returns advanced and revised carton quantities were negotiated. The software provider began development of the specified workflows.

6. Results and Transfer

The assignment delivered a financially evaluated operating model, $8 million in projected annual savings and identification of $2.5 million in excess and obsolete stock.

Implementation progressed through warehouse rationalization, inventory reduction, packaging changes and systems development. Gary helped establish momentum before the client continued the wider transformation.

Client testimonial

“We had ambition but no route to scale. Gary gave us clarity, challenged our assumptions, and delivered a practical plan we could execute. Our supply chain is now running faster, simpler, and without the firefighting.”

Chief Operating Officer, international accessories supplier

7. What This Practical Example Demonstrates

Gary connected customer responsiveness with the economics of inventory, configuration and distribution. Challenging those assumptions together revealed a way to support growth with less structural cost and complexity.

Growth readiness depends on whether the operating model can deliver the future customer promise economically and reliably.

Intervention Pathway: Operating Model Transformation.Delivery Model: Gary-led blueprint design, followed by assisted implementation and client-led continuation.